Project Description
Design and construct New Expansion Rail Yard and Gantry Rail to receive, load, and ship 100ft flat railcars with 14’-8” diam. steel wind towers.
Scope of Work
Design and construct approximately 5,000TF (track-feet) of ballasted Yard Tracks, two (2) UPRR #11 Turnouts, four (4) #9 Turnouts (pavement style), and sliding derails with all trackwork consisting of 115# CWR, wood ties, and concrete ties. All design and installation was performed per UPRR Standards.
Owner
Ameron International

12771 Imperial Highway
Santa Fe Springs, CA 90670
562.944.7985
info@japlacek.com
Links and Resources
The following railroad construction and maintenance resources, directories and associations are being provided for your convenience:
Railroad Resources and Directories
Project Name
Baldwin Avenue Grade Separation
Project Type
Design and Construction
Completion Date
June 2014
Location
El Monte, CA
Project Description
In coordination with UPRR, construct Double Shoofly Track for construction of new bridge for UPRR Mainline Tracks. As a Subcontractor to Sully-Miller Contracting, JA Placek Construction Co. was responsible for installation & removal of Shoofly Tracks.
Scope of Work
Construct approximately 3,000TF (track-feet) of Double Shoofly Tracks and one (1EA) Power Operated #15 Turnout with 136# CWR and Wood Ties. After completion of new bridge and new Mainline Tracks, remove and dispose 3,000TF of Shoofly Track.
Owner
Alameda Corridor East Construction Authority (ACE)
Additional Information
For more details visit https://www.theaceproject.org/

12771 Imperial Highway
Santa Fe Springs, CA 90670
562.944.7985
info@japlacek.com
Links and Resources
The following railroad construction and maintenance resources, directories and associations are being provided for your convenience: